Friday, May 27, 2016

Concrete Work Completed. Roadway Paving Next Week

Work Completed Last Week, May 23rd to May 27th
·         Concrete curb & gutter installation along entire project site
·         Concrete driveway replacement
·         Concrete sidewalk replacement

Work Anticipated to be completed Next week, May 30th to June 3rd  
·         Installation and final grading of aggregate base course within roadway
·         Paving 1st layer of asphalt pavement within roadway
·         Rough grading of landscape restoration areas.

Thank you to all the residents that are without access to their driveways throughout the week and over the Memorial Day weekend. Your patience and understanding is greatly appreciated. We understand the significant inconvenience this causes, but it is the most efficient way to get the project completed and eliminates the need to be out of your driveway multiple times.

The first layer of asphalt paving is scheduled to be completed next week. This will be a project milestone because it will eliminate most of the dust along the project site and provide a smooth driving surface.

No work will be performed on-site over the holiday weekend.

Have a fun and safe Memorial Day!!!