Monday, July 25, 2016

Major Construction Completed. Final Blog Post

Work Completed Last Week, July 18th to July 22nd 
·         Milled asphalt surface at intersection of Grove Street and Hutchings Avenue
·         Milled asphalt surface at intersection of MacLean Court and Hutchings Avenue
·         Final cleaning and work to prepare for paving the final layer of asphalt pavement
·         Applying layer of tack coat (oil) and sand prior to asphalt paving
·         Asphalt surface paving

Work Remaining to be completed
·         Repair damaged sidewalk at Grove Street and Hutchings Street
·         Continued watering of sod

The major construction operations along Hutchings Avenue is now completed. The only remaining items are to remove and replace a few vandalized sections of concrete sidewalk and continued watering of the previously installed sod. The contractor will continue to water the sod until a healthy stand of grass is established.

We are hopeful that you are happy with the improvements made to your street and neighborhood. We understand it was a long construction process and your patience has been greatly appreciated.

Since major construction is now completed, this will be the final Blog Post for the project. We hope you found the information provided in the blog useful regarding the construction progress and schedule for the upcoming weeks as well as providing information regarding the overall construction process.

If you have any further questions, concerns, or comments please contact the Village Project Manager, James Tigue, at 847-904-4334.

Thanks again for all your patience, understanding, and cooperation throughout the construction process.

Friday, July 15, 2016

Asphalt Surface Paving Scheduled for Next Week

Work Completed Last Week, June 11th to July 15th
·         Grading of area disturbed during construction
·         Installation and final grading of topsoil
·         Sod Installation
·         Adjusting structures to final grade
·         Performed final testing for underground utilities
·         Performed walk-through with Village staff to find any items that need additional work
·         Made minor repairs at locations identified by Village staff
·         General site clean-up

Work Anticipated to be completed Next week, July 18th to July 22nd
·         Asphalt surface paving
·         Milling asphalt surface at intersection of Grove Street and Hutchings Avenue
·         Milling asphalt surface at intersection of MacLean Court and Hutching Avenue
·         Repair damaged sidewalk at Grove Street and Hutchings Street

Paving of the asphalt surface layer is scheduled for next week. Additional information will be provided when the schedule is finalized regarding travel cautions and restrictions during the paving operations and prior when the existing asphalt will have a thin layer of oil sprayed on it.

The contractor has completed the landscape restoration with sod. The contractor will continue to water the sod until a healthy stand of grass is established.

The project is nearly completed with only the asphalt surface paving and a few other minor items of work to perform. Now that the sod is completed, hopefully you feel your yards are back to the way they were prior to the project starting.

Thanks again for all your patience, understanding, and cooperation during this long construction season.

Friday, July 1, 2016

Landscape Restoration Started

Work Completed Last Week, June 27th to July 1st
·         Limited work completed on-site
·         Asphalt driveway restorations completed
·         Began installation and final grading of topsoil
·         General site clean-up

Work Anticipated to be completed Next week, July 4th to July 8th  
·         No work over the July 4th Holiday
·         Complete installation and final grading of topsoil
·         Sod  Installation

Once the topsoil installation is completed, we request those residents with irrigation systems damaged during construction to please have them replaced and / or repaired by your irrigation contractor. It is typically easier for your irrigation contractor to repair the irrigation system after topsoil installation, but prior to sod installation.

Currently, the contractor is anticipating to perform the asphalt surface paving the week of July 11th.

Thanks again for your patience as the landscape restoration was delayed.

The contractor will not be on-site over the July 4th Holiday. Have a safe and enjoyable Holiday Weekend!!!