·
Milled asphalt surface at intersection of Grove
Street and Hutchings Avenue
·
Milled asphalt surface at intersection of
MacLean Court and Hutchings Avenue
·
Final cleaning and work to prepare for paving
the final layer of asphalt pavement
·
Applying layer of tack coat (oil) and sand prior
to asphalt paving
·
Asphalt surface paving
Work Remaining to be completed
·
Repair damaged sidewalk at Grove Street and
Hutchings Street
·
Continued watering of sod
The major construction
operations along Hutchings Avenue is now completed. The only remaining items
are to remove and replace a few vandalized sections of concrete sidewalk and
continued watering of the previously installed sod. The contractor will continue
to water the sod until a healthy stand of grass is established.
We are hopeful that you are
happy with the improvements made to your street and neighborhood. We understand
it was a long construction process and your patience has been greatly
appreciated.
Since major construction is
now completed, this will be the final Blog Post for the project. We hope you
found the information provided in the blog useful regarding the construction
progress and schedule for the upcoming weeks as well as providing information
regarding the overall construction process.
If you have any further
questions, concerns, or comments please contact the Village Project Manager,
James Tigue, at 847-904-4334.
Thanks again for all your
patience, understanding, and cooperation throughout the construction process.