Concrete curb & gutter installation along entire project site
·
Concrete driveway replacement
·
Concrete sidewalk replacement
Work Anticipated to be completed Next week, May 30th
to June 3rd
·
Installation and final grading of aggregate base course within roadway
·
Paving 1st layer of asphalt pavement within roadway
·
Rough grading of landscape restoration areas.
Thank you to all the residents that are without access to
their driveways throughout the week and over the Memorial Day weekend. Your
patience and understanding is greatly appreciated. We understand the
significant inconvenience this causes, but it is the most efficient way to get
the project completed and eliminates the need to be out of your driveway
multiple times.
The first layer of asphalt paving is scheduled to be
completed next week. This will be a project milestone because it will eliminate
most of the dust along the project site and provide a smooth driving surface.
No work will be performed on-site over the holiday weekend.
Have a fun and safe Memorial Day!!!