·
Resident Preconstruction Meeting held on
Wednesday, April 6th
·
Pot-holing existing utilities in preparation for
directional drilling of water main
·
Saw-Cutting existing pavement.
·
Mobilization of equipment
·
Product deliveries
·
Stake-Out of work to be performed
·
Internal televising of existing sewers along
project site
Work Anticipated to be complete Next week, April 11th
to 15th:
·
Excavation of boring pits needed for directional
drilling of water main
·
Installation of water main via directional
drilling
·
Open cut installation of new fire hydrants along
the site.
Next week will be the start of heavy construction. There
will be two methods utilized to install the water main. The first is via
directional drilling. In this method, a steel rod and cutter is drilled under
the existing pavement and ground. Once a hole large enough for the new water
main is created, the new water main pipe is pulled through the hole. This
method does not require the contractor to excavate a trench along the entire
roadway to install the new water main pipe. This method will be used to install
the long sections of pipe.
The second method is Open Cut. As the name suggests, a hole
or trench is excavated within the existing ground. The new water main piping is
then installed within the trench and backfilled. This method will be used to
make connections to the existing water main, install fire hydrants, install and
connect water services, and other instances as needed.
As construction starts, we will do everything possible to
minimize the inconvenience to your daily lives; however, we understand
construction is disruptive so we appreciate your patience and understanding
throughout the construction process. We will do our best to provide as much information
as possible and provide advance notice for any inconveniences that you will be
caused.
No comments:
Post a Comment